Add the units of internal work a project needs, break the big ones down, keep their details current, and clear them as they are finished. Firm staff work from the project's Tasks tab.
Add a task
- Open the project.
- Select the Tasks tab.
- Select Add Task, or the + button in the task list.
- Enter the Task Name, for example "Gather client documents".
- Select the Assign field and choose the responsible staff member.
- Set a Due Date.
- Tasks without a due date do not appear in Reports - Project Performance.
- Select Save.
Change a task's assignee, due date or status
- Open the project and select the Tasks tab.
- Select the task row to open its detail panel.
Select the field you want to change and update it:
- Task Name
- Assign
- Due Date
- Status
If you don't know who should take the task, leave Assign empty and tick Show this task in work pools (above Task Dependencies). The task appears on the Work Pool tab on the Home dashboard for a staff member to claim. See Add projects, stages and tasks to work pools.
- Select Save.
Reorder tasks
- Open the project and select the Tasks tab.
- Drag a task to its new position in the list.
Mark a task complete
- Open the project and select the Tasks tab.
- Complete the task one of two ways:
- Select the checkbox next to the task name.
- Open the task and set Status to Completed.
Delete a task
- Open the project and select the Tasks tab.
- Select the task to open its detail panel.
- Select Delete.
- Select Confirm.
Related
- Project, task and request status reference
- Create a project
- Manage a project record
- Tasks, requests and deliverables